Middle school financials released

1

By Joseph Brown-

Overcrowding and decrepit facilities could soon be eased if construction of a new middle school, physical education gymnasium and multipurpose activity center gets approved. Dover School Board members have approved a budget of $14,307,937 to be generated from a millage and state funding.
In the September 17 election the school district will ask taxpayers for an increase of 5.5 mills. Personal property taxes are computed from 20% of an assigned appraisal value multiplied by the school districts millage rate. The 5.5 mill increase will put the Dover School District with the highest rate in the county at 45.8 mills.
The addition to the middle school will be replacing a 34,000 square foot building that was built in 1956. The Arkansas Division of Public School Academic Facilities and Transportation has placed a -14% depreciated value on the building and has provided $4,617,937.85 towards its renovation and addition.
The proposed plan will add 28 classrooms and renovate 10 in the building formerly referred to as the Intermediate School. It will be 36,246 additional square feet including a FEMA approved safe room, state of the art media center and computer labs. The total bill for the building will be approximately $7,326,000.
The physical education/ gymnasium will replace the WPA (Old) Gym built in 1939. The state has placed a -48% depreciated value on the building. The new facility will be 13,150 square feet and consist of two full length basketball courts, two locker rooms and removable bleachers. It will cost approximately $1,971,360.
The multipurpose activity center will be 34,580 square feet and consist of a 40-yard indoor football practice field, locker rooms, coach’s offices, film rooms, weight rooms and batting cages. The football program is currently housed in the back building of the former primary school built in 1963. The building will be available to other activities including baseball, softball, track and marching band. It will also be available to the community through youth athletics and other activities. This project will cost approximately $3,885,000.
The total bill for the three buildings is estimated at 13,182,360 with the additional 1,125,577 being used for security and furnishings. Further input is welcomed from the community at the Continue the Progress meetings held the every other Tuesday. The next is scheduled for July 2 at the Middle School.